Key Milestone Dates

Our Key Milestone Dates are mentioned below.

Track First Name Start CRP UAT Go-Live
W01 Oracle Fusion Finance - 17 Units 5-Jun-16 3-Oct-16 21-Dec-16 2-Jan-17
W01 Core HCM (GCC), Payroll (UAE) 5-Jun-16 3-Oct-16 21-Dec-16 2-Jan-17
W02 Oracle Fusion Finance - 14 Units 9-Jan-17 27-Feb-17 3-May-17 28-May-17
W02 Payroll Rollout - Other GCC 9-Jan-17 27-Feb-17 3-May-17 28-May-17
W03 Advance HCM - All GCC 9-Jan-17 27-Feb-17 3-May-17 28-May-17
W03 Oracle Fusion Incentive Compensation 9-Jan-17 27-Feb-17 3-May-17 28-May-17
W13 PBCS 9-Jan-17 23-Mar-17 21-May-17 28-May-17
W05 Oracle Retail 2 Brands 7-Aug-16 10-Feb-17 23-May-17 20-Sept-17
W06 Merchandising Insight 11-Apr-17 6-Jun-17 13-Aug-17 20-Sept-17
W09 Oracle Retail - POS 14-Mar-17 6-Jun-17 13-Aug-17 20-Nov-17
W04 Oracle Fusion Finance - 14 Units 4-Jun-17 11-Jul-17 17-Aug-17 30-Aug-17
W04 Oracle HCM India 4-Jun-17 11-Jul-17 17-Aug-17 30-Aug-17
W14 PBCS 10-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17
W10 Oracle Retail MFP 17-Jul-17 27-Sep-17 3-Dec-17 17-Dec-17
W08 Oracle Retail - All GCC 21-Aug-17 14-Jan-18 25-Feb-18 11-Mar-18
W11 Oracle Retail - All brands & India 12-Feb-18 8-Apr-18 27-May-18 10-Jun-18
W12 Oracle Retail RDF + AP 25-Dec-17 8-Apr-18 27-May-18 10-Jun-18